Energy and Emissions Reduction - Northern Territory

This Schedule will support the investigation, design, installation and commissioning (excluding maintenance) of the Northern Territory's: 

  • initial 32.6 megawatt/34.7 megawatt/hour battery energy storage system (BESS) in the Darwin-Katherine interconnected system; and 
  • remote power system and microgrid projects in remote First Nations communities. 
Topic(s)
Environment
Department/Agency
Climate Change
State/Territory
NT
Total funding
$30.00m
Agreement type
FFA - Environment
Start date
18 May 2023
End date
30 June 2024
Expired agreement
Yes